Tennis Court Lights

The current lack of lighting on MISD high school tennis courts prevents extended practice and playing time as compared to surrounding area districts.  Installing LED lighting on MISD high school tennis courts will allow players and coaches to extend play from early morning practices into the evening for late matches and tournaments.  In addition to extended playing time, providing adequate lighting will allow players a safe, well-lit area to practice and play. 

WAG

 

Project Information:

  • Package #A6  Tennis Court Lights     

  • Total Project Cost (Architect, General Contractor, Fees, Equipment)-$1.691 Million 

  • Estimated Completion April 2025

  • The construction budgets for the Bond Program encompass architect fees and all related expenses.

Project budgets can change during design, and completion dates are subject to change based on weather, materials availability, and contractor labor irregularities.  

PURCHASE ORDER INFORMATION:
PO# VENDOR DESCRIPTION DOLLAR AMOUNT

9582500076 

Groves Electric 

Install Tennis Court Lights at all 5 High Schools 

$1,687,600.00 

9582500074 TriStar Pipe Inspection Tennis Court Line Locate $1,750.00
9582500201 GeoTex Legacy HS Tennis Materials Testing $1,848.00

 

Project Goals:

  • Install LED lighting at all high school tennis courts 

Progress:

  • Voters Approved BOND May 4, 2024 

  • Bond Sales for Phase 1 Completed June 25, 2024 

  • Board approves Huckabee & Associates as Primary Architect May 2024 

  • General Contractor- Groves Electric

  • All proposers were on either Buy Board or another purchasing Co-Op. Four proposers were contacted and given bid documents.
  • Received two proposals, Musco Sports Lighting & Groves Electric were the best overall value for the district.
  • All underground raceways have been installed at each location.
  • Summit & Timberview High Schools poles installed and working.
  • Mansfield High School poles have been delivered installation is on schedule.
  • Project should be completed at all locations March 2025.
  • All light poles are installed and working, the contractor is going back to each location and repairing any damaged irrigation lines that have been identified by the Bond Department and Maintenance.
  • Damaged Irrigation has been repaired and close out documents have been delivered.
  • Project Completed

CONNECT WITH US:

Email | MISD2024Bond@misdmail.org
Address | 605 E. Broad Street, Mansfield, TX 76063

NEED TO TALK TO  SOMEONE?

Jeffrey S. Brogden, Associate Superintendent Facilities
and Bond Programs  
Phone I 817-299-4345 
Email I Jeffreybrogden@misdmail.org