Our Schools

Auxiliary Buildings Schools

Package T6 allows the district to upgrade its infrastructure to address aging systems and meet increasing demands with technology, as well as provide equipment with the latest technological advancements.  

Step 3 graphic

 

Project Information:

  • Package #T6 – Technology Infrastructure – Auxiliary Buildings  

  • Estimated Completion July 2025 

  • Total Project Cost (Architect, General Contractor, Fees, Equipment)-$12.352 million 

  • The construction budgets for the Bond Program encompass architect fees and all related expenses.

Project budgets can change during design, and completion dates are subject to change based on weather, materials availability, and contractor labor irregularities.  

PURCHASE ORDER INFORMATION:
PO# VENDOR DESCRIPTION DOLLAR AMOUNT

9582500045 

CDW-G 

Switches and Power Supplies Auxiliary Buildings  

$899,616.14  

9582500039 

CDW-G 

Wireless Access Points – Auxiliary Buildings 

 $680,820.00 

9582500027 

CDW-G 

Wireless Access Points Center for Performing Arts 

 $493,279.83

9582500159 CDW-G Wireless Upgrades-Center for Performing Arts $14,633.33
9582500168 CDW-G Newsom Off-Site Infrastructure Firewall $106,240.86
9582500196 CDW-G Natatorium Switches $24,912.70
9582500222 CDW-G Nutanix Software Bundle $1,367,612.56 
9582500223 CIS NOS Battery Backup $20,814.58
9582500238 CDWG Natatorium Switch Addition $12,456.35
9582500287 Communications Plus Student Nutrition Battery Back-Up $6,845.00
9582500288 Communications Plus Maintenance Facility Battery Back-Up $6,845.00
9582500286 Communications Plus RLA Stadium Battery Back-Up $12,640.00
9582600139 CDWG NOC Cooling System $1,351,700.00
9582600140 CDWG NOC DNAC XL Appliance $138,809.00
9582600141-5 CDWG Aux. Data Cabling $206,065.75

 

Project Goals:

  • Replace building battery backup for UPS units 

  • Fiber Upgrades at select buildings 

  • Data Wire Upgrade at select buildings  

  • Replace Network Switches 

  • Upgrade Wireless Access Points 

  • Replace access control for MDF and IDF closets 

Progress:

  • Voters Approved BOND May 4, 2024 

  • Bond Sales for Phase 1 Completed June 25, 2024 

CONNECT WITH US:

Email | MISD2024Bond@misdmail.org
Address | 605 E. Broad Street, Mansfield, TX 76063

NEED TO TALK TO  SOMEONE?

Jeffrey S. Brogden, Associate Superintendent Facilities
and Bond Programs  
Phone I 817-299-4345 
Email I Jeffreybrogden@misdmail.org