Our Schools

Mansfield HS Baseball and Softball

The current conditions at MISD baseball and softball fields have downfalls that result in less practice and playing time than surrounding area districts.  Installing turf on MISD baseball and softball fields as well as covered batting cages will allow players and coaches to continue play even in the midst of inclement weather.  In addition to extended playing time, turf provides a more durable and low maintenance option for the fields reducing upkeep costs in the long term.

Constrcution

 

Project Information:

  • Package #A1 MHS Baseball and Softball  

  • Total Project Cost (Architect, General Contractor, Fees, Equipment)-$6.732 Million 

  • Estimated Completion December 2025

  • The construction budgets for the Bond Program encompass architect fees and all related expenses.

Project budgets can change during design, and completion dates are subject to change based on weather, materials availability, and contractor labor irregularities.  

PURCHASE ORDER INFORMATION:
PO# VENDOR DESCRIPTION DOLLAR AMOUNT

9582500058 

Huckabee & Associates 

Architectural Services 

$626,494.51 

9582500110 Core Construction Pre-Construction $10,000.00
9582500142 Raba Kistner GeoTechnical Services $11,700.00
9582500148 Tri-Star Pipe Inspection Private Line Locate, BBSB $625.00
9582500240 Raba Kistner MHS BBSB GeoTech $8,000.00
9582500300 Core Construction MHS BBSB GMP $5,976,120.00

9582500305

Terracon Asbestos Survey BBSB $1,023.00
9582600050 Raba Kistner Materials Observation Testing $80,625.44
9582600093 Texas Dept. of State/Health Services MHS Asbestos Notification $57.00
9582600108 C&H Baseball MHS BBSB Turtle Cage $12,500.80
9582600110-1 Grainger MHS BBSB Cord Reels $5,7412.42

 

Project Goals:

  • Install turf on baseball and softball field 

  • Install covered batting cages 

Progress:

  • Voters Approved BOND May 4, 2024 

  • Bond Sales for Phase 1 Completed June 25, 2024 

  • Board approves Huckabee & Associates as Primary Architect May 2024 

  • Construction Manager at Risk- Core Construction (RFP Issued July 29, 2024) 

  • Community Site Visits

  • The final GMP was approved at the May board meeting and Notice to Proceed has been issued to Core Construction
  • Final site walks have been conducted with Athletics, the MISD Maintenance Department, Huckabee Architects, and Core Construction in preparation for groundbreaking.
  • GeoTechnical reports have been issued and reviewed by Huckabee Architects and Sports Design Group, with site preparation recommendations finalized.
  • Construction is scheduled to begin this month with substantial completion targeted for December 31, 2025.

CONNECT WITH US:

Email | MISD2024Bond@misdmail.org
Address | 605 E. Broad Street, Mansfield, TX 76063

NEED TO TALK TO  SOMEONE?

Jeffrey S. Brogden, Associate Superintendent Facilities
and Bond Programs  
Phone I 817-299-4345 
Email I Jeffreybrogden@misdmail.org