Mansfield HS Baseball and Softball
The current conditions at MISD baseball and softball fields have downfalls that result in less practice and playing time than surrounding area districts. Installing turf on MISD baseball and softball fields as well as covered batting cages will allow players and coaches to continue play even in the midst of inclement weather. In addition to extended playing time, turf provides a more durable and low maintenance option for the fields reducing upkeep costs in the long term.

Project Information:
-
Package #A1 MHS Baseball and Softball
-
Total Project Cost (Architect, General Contractor, Fees, Equipment)-$6.732 Million
-
Estimated Completion December 2025
-
The construction budgets for the Bond Program encompass architect fees and all related expenses.
Project budgets can change during design, and completion dates are subject to change based on weather, materials availability, and contractor labor irregularities.
PURCHASE ORDER INFORMATION:
| PO# | VENDOR | DESCRIPTION | DOLLAR AMOUNT |
|
9582500058 |
Huckabee & Associates |
Architectural Services |
$626,494.51 |
| 9582500110 | Core Construction | Pre-Construction | $10,000.00 |
| 9582500142 | Raba Kistner | GeoTechnical Services | $11,700.00 |
| 9582500148 | Tri-Star Pipe Inspection | Private Line Locate, BBSB | $625.00 |
| 9582500240 | Raba Kistner | MHS BBSB GeoTech | $8,000.00 |
| 9582500300 | Core Construction | MHS BBSB GMP | $5,976,120.00 |
|
9582500305 |
Terracon | Asbestos Survey BBSB | $1,023.00 |
| 9582600050 | Raba Kistner | Materials Observation Testing | $80,625.44 |
| 9582600093 | Texas Dept. of State/Health Services | MHS Asbestos Notification | $57.00 |
| 9582600108 | C&H Baseball | MHS BBSB Turtle Cage | $12,500.80 |
| 9582600110-1 | Grainger | MHS BBSB Cord Reels | $5,7412.42 |
Project Goals:
-
Install turf on baseball and softball field
-
Install covered batting cages
Progress:
-
Voters Approved BOND May 4, 2024
-
Bond Sales for Phase 1 Completed June 25, 2024
-
Board approves Huckabee & Associates as Primary Architect May 2024
-
Construction Manager at Risk- Core Construction (RFP Issued July 29, 2024)
-
Community Site Visits
- The final GMP was approved at the May board meeting and Notice to Proceed has been issued to Core Construction
- Final site walks have been conducted with Athletics, the MISD Maintenance Department, Huckabee Architects, and Core Construction in preparation for groundbreaking.
- GeoTechnical reports have been issued and reviewed by Huckabee Architects and Sports Design Group, with site preparation recommendations finalized.
- Construction is scheduled to begin this month with substantial completion targeted for December 31, 2025.
CONNECT WITH US:
Email | MISD2024Bond@misdmail.org
Address | 605 E. Broad Street, Mansfield, TX 76063